18 March 2008
Electric and Some Insulation
Shop is progressing but slowly, the rough in electric was mostly approved by the inspector. Just have to bury the feed line as soon as the ground thaws enough to dig. The insulation subcontractor was here to put the stuff up that holds the insulation in. We are using blown in cellulose. Yesterday most of the shop got insulated and there was only about a half a day to finish but they never came back today. Our contractor was on the phone to see what the hold up is. We are scheduled to have dry wall loaded in via boom truck tomorrow and it may not happen since the insulation isn't done yet. Ah the joys of sub-contractors!
But we are making progress.